A basement bedroom in Ottawa needs a window a person can escape through, with an unobstructed opening of at least 0.35 m² and no dimension smaller than 380 mm, plus enough ceiling height, a smoke alarm and a building permit. If the window opens into a window well, the well needs at least 550 mm of clearance in front of the window.

Those are the Ontario Building Code figures for a bedroom. Many contractor websites quote a different set of numbers (0.38 m², 460 mm, a 1 m well) as the bedroom rule. Those come from the Ontario Fire Code and apply to a different situation. This guide separates the two, then gives what it has actually cost on our projects to make a basement window legal.

If you are finishing the whole basement, see our basement finishing service. Our designers confirm every one of these requirements on the permit drawings.

The Egress Window Rule (Ontario Building Code 9.9.10.1)

The Building Code requires every floor level that contains a bedroom to have at least one outside window that can be used to get out in a fire, unless a door on that level leads directly outside. In a basement that means at least one compliant window, and the right place for it is in the bedroom itself. Where there are two bedrooms downstairs, we design one for each. The window has to meet all of these:

  • It opens from the inside without keys, tools or special knowledge. No removing a sash, no security bars that need a key.
  • An unobstructed open area of at least 0.35 m² (about 3.8 sq ft).
  • No dimension of the opening less than 380 mm (15 inches), in height or in width.
  • It stays open on its own without a prop.
  • If it opens into a window well, at least 550 mm (about 22 inches) of clear space in front of the window. A sash that swings outward must not reduce that clearance in a way that blocks escape, and a well deeper than 1 m needs a way to climb out.

The numbers describe the hole you climb through, not the size of the glass or the frame. This is where most windows fail.

The City of Ottawa published an advisory on egress windows in August 2025 confirming these figures under the 2024 Building Code. The 1,000 mm maximum sill height that applies on upper floors does not apply in a basement, but a high sill still has to be climbable, so we plan a built-in step or bench under it.

Why a typical basement slider fails

The standard basement window in an Ottawa house is a horizontal slider roughly 30 inches wide and 15 to 18 inches high. Only half of a slider opens. Half of 30 inches is 15 inches wide, minus the frame, and the opening is under the 380 mm minimum and far under 0.35 m². It does not matter that the whole window looks big enough.

The window styles that pass in a small opening are the ones where the entire sash clears: an inswing casement or a tilt-and-turn. Both show up on our jobs for exactly this reason.

The Numbers Other Sites Get Wrong

Two different laws set escape window sizes in Ontario, and they are easy to mix up.

Ontario Building CodeOntario Fire Code, Section 9.8
Applies toNew work done under a building permit, including a new basement bedroomExisting two-unit houses that do not meet the Building Code, such as older or unpermitted basement apartments
What the window is forEscape from a bedroomA second way out of the dwelling unit
Minimum open area0.35 m²0.38 m²
Minimum dimension380 mm460 mm
Window well clearance550 mm1 m
Enforced byCity of Ottawa Building Code ServicesOttawa Fire Services

If you are adding a bedroom to your own basement under a permit, the Building Code column is yours. If you own an older house with an existing basement apartment that was never permitted, the Fire Code column is the one an inspector will hold you to. A suite built under permit to the current Building Code is governed by the Building Code.

Ceiling Height for a Basement Bedroom

For new construction, the Building Code asks for a bedroom ceiling of 2.3 m over at least half of the required floor area, or 2.1 m over all of it. Few Ottawa basements have that.

Two provisions make basement bedrooms workable in existing homes:

  • Secondary suites. A basement that is a separate dwelling unit needs 1.95 m of clear height, and 1.85 m under beams and ducts.
  • Existing houses. For a house that is at least five years old, the renovation part of the Code can accept a lower ceiling than the new-construction figure. Which allowance applies to your basement is settled at plan review, so we confirm it on the drawings before anything is framed.

Measure from the slab to the underside of the joists, then subtract what you are about to add: a subfloor takes 25 to 50 mm and a drywall ceiling another 16 to 40 mm. Then measure again under the main beam and the largest duct. If the finished number is not going to work, the options are rerouting ducts, a different floor system, or lowering the floor. That last one is covered on our basement underpinning and lowering page.

Bedroom Size, Alarms and the Other Requirements

  • Size. The Building Code sets a minimum bedroom area of 7 m² (about 75 sq ft), or 6 m² where there are built-in closets.
  • Smoke alarms. A hardwired, interconnected smoke alarm in the bedroom and on each storey, so that one sounding triggers them all.
  • Carbon monoxide alarm. Near the sleeping area when the house has a fuel-burning appliance or an attached garage.
  • Heat and ventilation. A supply of heat to the room, and the house ventilation extended to serve it.
  • Insulation and vapour control. Finished basement walls have to be insulated and protected from moisture to current standards.
  • Electrical. New circuits are inspected by the Electrical Safety Authority, separately from the City's building inspections.

Do You Need a Permit to Add a Basement Bedroom?

Yes. Creating a bedroom means framing, electrical and insulation, and it changes how the space is used. The City of Ottawa renovation permit fee in 2026 is $12.75 per $1,000 of construction value with a $117 minimum, and starting without one adds a 50 percent surcharge. See basement renovation permits in Ottawa.

There is a practical reason too. A room without a legal egress window cannot be listed as a bedroom when you sell, and unpermitted work becomes the buyer's negotiating tool. See selling a house with unpermitted work in Ottawa.

What an Egress Window Costs in Ottawa

These are client prices before HST from itemized work on our 2024 to 2026 projects.

ScopeWhat it has cost on our jobsWhen this applies
Egress-rated window in the existing opening$1,000 to $2,500 per windowThe rough opening is already big enough; a casement or tilt-and-turn replaces the slider
Three windows for a basement suiteAbout $3,000 to $5,200Egress windows for bedrooms and living room, existing openings
Cut the concrete, new egress window and window well$5,500 to $10,000 per openingThe opening has to be enlarged downward or sideways
Window wells for two front egress windowsAbout $6,400Excavation, wells and drainage only, windows separate
Reworking an existing window wellAbout $1,100The window is fine but the well is too tight

The jump from the first row to the third is the concrete. Enlarging an opening in a poured foundation means a wet saw cut, a new lintel if the opening gets wider, waterproofing the new edges, excavation outside, a well that drains to the weeping tile, and backfill. Cutting down to lower the sill is simpler than cutting sideways, because widening affects what the wall above is resting on.

What moves the price within the range:

  • How far below grade the new sill is. Deeper wells cost more and need better drainage.
  • Poured concrete or block. Block is easier to cut but needs the cores filled and a proper lintel.
  • What is outside. A driveway, a deck, a gas meter or a neighbour's wall 1.2 m away all complicate the dig.
  • Whether the opening gets wider. A wider opening needs an engineered lintel. A structural review has cost $750 to $950 on our projects.

Egress Window Planning Tips

  • Put the bedroom where the best window already is. Planning the layout around an existing large opening can save several thousand dollars.
  • Check the side yard. A window well needs room. Narrow side yards in older neighbourhoods like the Glebe, Hintonburg and Westboro sometimes leave only the front or back wall as an option.
  • Use a casement or tilt-and-turn. They give the largest clear opening for the size of the hole.
  • Think about snow. A well cover keeps it usable in February, but it has to open from inside without tools.
  • Do it before finishing. Cutting concrete makes slurry and dust. It belongs at the start of the job, not after the drywall.

Frequently Asked Questions

What makes a basement bedroom legal in Ontario?

An egress window or door that meets the Building Code (0.35 m² open area, no dimension under 380 mm, opens from inside without tools), adequate ceiling height, the minimum floor area, smoke and carbon monoxide alarms, and a building permit with passed inspections.

How big does a basement bedroom window have to be in Ottawa?

The clear opening must be at least 0.35 m² with no dimension less than 380 mm. A window with a clear opening of 380 mm by 925 mm just meets it, and so does one about 600 mm square.

Does a basement bedroom need a window well?

Only if the window is below grade. If it is, the well needs at least 550 mm of clearance in front of the window.

How much does it cost to enlarge a basement window for egress?

On our projects, $5,500 to $10,000 per opening for the concrete cut, the window and the well, before HST. If the existing opening is already large enough, a new egress window alone is $1,000 to $2,500.

What is the minimum ceiling height for a basement bedroom in Ontario?

New construction requires 2.3 m over half the room or 2.1 m throughout. A secondary suite needs 1.95 m, with 1.85 m under beams and ducts. Existing houses can qualify for reduced heights under the Code's renovation provisions, which is confirmed at plan review.

Adding a Bedroom Downstairs?

We check the window, the well, the ceiling height and the layout before you spend anything, and show you the finished room in a free 3D design concept. See what a full basement costs in our basement renovation cost guide, read about basement renovations in Ottawa, or request a free quote.

Want A Free Quote? We Can Help.

Get a free no-obligation quote for your next project in seconds.

Thank you! Your submission has been received!
Oops! Something went wrong while submitting the form.
Recent Posts
CallFree Quote
Live Chat